Pudding Lane repairs result of two year battle.

 We have during the year received confirmations that repairs would be made along Pudding Lane.

On 3rd November 2022 this email was received from Essex Council:

Reference Number: 2682118
Issue: verge defects (this relates to ditches in side verges causing vehicles to topple)
Location: PUDDING LANE

Current status: works completed

Good news - we have now completed works at this site. Thanks for helping us to keep Essex roads in the best condition we can.

Regards,

Essex Highways


Image of verges causing safety hazards to vehicles

Read more (here)

------------------------------------------------------------------------------------------------------------

Other dangerous verges were also reported and this email was also received on 3rd November 2022:

Reference Number: 2682117
Issue: verge defects
Location: PUDDING LANE

Current status: this issue has been made safe

We have investigated, risk assessed and recorded the issue, and initial works to make it safe have been completed. A further assessment will be carried out to establish whether a permanent repair is required in the future. Thanks for helping us keep Essex roads in the best condition we can.

Regards,

Essex Highways

---------------------------------------------------------------------------------------------------------------

On 22nd November 2022 this email was received from Essex Council:

Reference Number: 2682580 
Issue: signing defects (relating to chevrons along Pudding Lane)
Location: PUDDING LANE

Current status: inspection outcome

We have investigated, risk assessed and recorded this issue and we are in the process of scheduling works.

Regards,

Essex Highways


Image of Chevrons as they were at the time of report.

You can read more (here)


--------------------------------------------------------------------------------------------------------------------

On the same day this email was also sent:

Reference Number: 2683317
Issue: bollards and railings  (this would be for the alternate set of bollards from the set in image below)
Location: PUDDING LANE

Current status: inspection outcome

We have investigated, risk assessed and recorded this issue and we are in the process of scheduling works.

Regards,

Essex Highways

-----------------------------------------------------------------------------------------------------------------------

Image of bollards as of when reported on 7th October 2020.

Reference Number: 2683318
Issue: bollards and railings
Location: PUDDING LANE

Current status: inspection outcome

We have investigated, risk assessed and recorded this issue and we are in the process of scheduling works.

Regards,

Essex Highways

You can read our original report (here)


Wilson Chowdhry, writer for the Chigwell Row Community blog, said:

"I noticed some changes to Pudding Lane over the last year and this year and the council has been emailing updates.

"It's great to see the regular reports submitted to the council have had an effect, though the length of time taken to resolve issues is less than satisfactory.

"At least we know we can get things done and I encourage people to share further road matters so that we can keep a public record.

"Together we can make our streets safer.

We would like to hear from local residents about the recent repairs. Have the works concluded and if so do they satisfy the needs of local residents.

Please email:  wilson@eastilfordbettermentpartnership.org




Comments

Popular posts from this blog

Community Unites in Mourning and Tribute as Murder Trial Looms for Slain Youth Daniel Anjorin

Justice Unveiled: Preliminary Proceedings in the Hainault Sword Attack Trial

Multiple Victims Stabbed by Sword-Wielding Attacker Following Van Crash into Hainault Residence